The bricks are being installed on the exterior of the building as interior walls are going up. Below is a close up of the front façade brick and cast stone details.
Scaffolding has been erected at the rear façade the entire height of the building to facilitate masonry and cast stone detail. After that is complete, the windows will be installed.
Here's a video of the scaffolding being erected.
The interior of an apartment. All of the electical work is done and phone/data/cable connections have been installed by Time Warner Cable and Verizon. The walls have been closed up and priming/painting to begin shortly.
The bathtubs are in place and tiling has started.
For more information about the building, as well as photos from the July 2007 groundbreaking ceremony, please click here.